Frontier 53 Phase 3

Phase 3 will take place over a three-year period, spanning the 2025–2027 construction seasons. The scope of work includes a 1.15 km extension of the main Tamarack Trail spine along Little Wabush Lake, a 200 m pathway connecting Gateway Labrador to the Town’s recreation area on Booth Avenue, and a 250 m bypass segment that will divert pedestrian traffic around a section of the White Wolf Snowmobile Club trail to allow for safe seasonal use.

No News Currently

Hidden
Hidden
Who's Listening?
Craig Purves
Director of Planning and Development
Town of Labrador City
Timeline
Project Launch & Permitting
Initial planning activities begin. Permits are secured and construction is scheduled to avoid sensitive nesting seasons.
Early Construction – Priority Segments
Work begins on the Snowmobile Trail Bypass and the Gateway Link near Booth Avenue. These high-priority sections improve safety and access.
Main Trail Construction – Tamarack Segment
The 1.15 km Tamarack Trail extension along Little Wabush Lake is constructed in stages over the 2026–2027 seasons.
Signage & Gate Installation
Trail signage and access control gates are installed throughout the new segments to enhance wayfinding and protect users.
Project Completion & Close-Out
All construction wraps up by November 2027. Final claims are submitted by February 2028.